PlanningBy the Ambient Civil team4 min read

Quote or estimate?

A quote is a price for a defined scope of work. If the scope doesn't change, the price shouldn't either. An estimate is a best guess that can move. Civil work involves ground you can't see, so many quotes are fixed for the known work, with provisional sums for the unknowns. That's normal; what matters is that it's clear.

The comparison checklist

Item What to look for Red flag
Scope A clear description, ideally with drawings, levels and areas "Demolish house and clear site" with nothing else
Exclusions A written list of what isn't included No exclusions at all (they show up later as variations)
Provisional sums Allowances for rock, groundwater, soft ground, contamination or asbestos, with rates Unknowns ignored, or a very low allowance
Consents and engineering Who applies, who pays the fees, who engages the engineer Silence, or "by others" without saying who
Disposal Where spoil and waste go, and whether you'll get dockets No mention of disposal or tip fees
Reinstatement Lawns, paths, fences and the road crossing put back Excluded without saying so
Programme Start date, duration and how weather is handled No timeframe
Insurance Public liability insurance, and contract works cover for larger jobs Can't produce a certificate
Health and safety A site-specific safety plan; traffic management where needed No plan
Licences Licensed drainlayer for drainage; licensed asbestos removalist; licensed building practitioners for restricted building work The licensed trade "can sort it" without names
Payment terms Deposit, progress claims tied to milestones, retentions Large upfront payment before work starts
Variations How changes are priced and agreed, in writing, before the work is done "We'll sort it out at the end"

What are provisional sums and PC sums?

  • A provisional sum is an allowance for work that can't be fully priced yet, such as rock excavation or contaminated soil. The final cost is adjusted to the actual quantity, so compare the rates, not just the allowance.
  • A prime cost (PC) sum is an allowance for materials or items you'll choose later, such as pavers or fittings. The final cost changes with your choice.

A quote with a low total and big provisional sums can end up costing more than one that priced the risk honestly.

Your rights on residential building work

For residential building work, New Zealand law gives homeowners specific protections:

  • $30,000 or more (including GST): there must be a written contract, and the contractor must give you a disclosure statement and the standard checklist before you sign. You can ask for them on smaller jobs too.
  • Implied warranties apply to residential building work whatever the contract says, for example that the work is done competently and complies with the Building Code.
  • A 12-month defect repair period applies after the work is finished: tell the contractor about defects in that time and they must fix them.

Questions worth asking every contractor

  1. Have you done this kind of job, in this kind of ground, recently? Can I see photos or speak to a client?
  2. Who will be on site day to day, and are they your own staff?
  3. What's most likely to change the price, and how have you allowed for it?
  4. Who handles consents, engineering, inspections and sign-offs?
  5. Where does the waste go, and will I get disposal records?
  6. What does the site look like when you leave?
  7. Can I see your insurance certificate and safety plan?

Why the cheapest quote isn't always the cheapest job

The lowest number often comes from leaving things out: disposal, reinstatement, drainage, the vehicle crossing, consents or a realistic rock allowance. Those come back as variations once you're committed. Compare like with like, then choose on value, communication and track record.

How Ambient Civil quotes

We visit the site for free, then give you an itemised, fixed quote with exclusions and provisional sums stated plainly, usually within five working days. We hold $5 million public liability insurance and WorkSafe Class A and B asbestos licences, and run every site under a documented health and safety plan. Ask for a quote.

For job-specific cost guides, see house demolition, retaining walls, earthworks and driveways.

Sources and further reading

General information only. Every site is different: consent, engineering and safety requirements depend on your property, so check with Auckland Council or a qualified professional, or ask us for a free site visit.

About this guide. Written by the Ambient Civil team: 22 in-house crew and 20+ years of civil construction, demolition and earthworks across Auckland. Rules and licence requirements are summarised from the official sources listed above and were checked on . Rules change, so confirm your property's position with Auckland Council or a qualified professional.

All guides->