What does Exemption 20 actually say?
Schedule 1 of the Building Act 2004 lists work that doesn't need building consent. Exemption 20 covers a retaining wall that:
- retains no more than 1.5 metres depth of ground, and
- does not support any surcharge or any load additional to the load of that ground.
The technical guidance also expects the wall to drain groundwater from behind it, because water pressure is the most common reason walls fail.
If both conditions are met, no building consent is needed. If either isn't, the wall needs building consent.
How is the 1.5 m measured?
Measure the depth of ground retained: the vertical difference between the finished ground level in front of the wall and the ground level it holds back. That isn't always the visible height of the wall. A wall might stand 1.2 m out of the ground but retain 1.6 m because the ground behind it is higher than the top of the wall, or because the ground in front has been dug away.
What counts as a surcharge?
A surcharge is any load on the retained ground beyond the soil itself. Common surcharges on Auckland sites:
- a driveway, parking area or turning bay above the wall;
- a building, deck or foundation within reach of the wall;
- sloping ground rising behind the wall;
- another retaining wall above it (tiered walls), if it's close enough to load the lower one;
- a swimming pool, water tank, or heavy storage above.
If a surcharge applies, even a 600 mm wall needs building consent and engineering.
Retaining wall consent scenarios
| Scenario | Building consent? |
|---|---|
| 1.2 m garden wall, flat lawn above | Usually exempt (Exemption 20), if it drains properly |
| 1.0 m wall with a driveway along the top | Needs consent: the driveway is a surcharge |
| 1.8 m wall, flat ground above | Needs consent: retains more than 1.5 m |
| Two 1.2 m walls stepped close together | Likely needs consent: the upper wall can surcharge the lower one, so ask an engineer |
| Wall supporting a house foundation | Needs consent |
| Wall in a rural zone retaining up to 3 m | Can be exempt under a separate rural exemption (Exemption 41) if designed or reviewed by a Chartered Professional Engineer |
Does an exempt wall have to meet the Building Code?
Yes. Exempt means "no consent needed", not "no rules". An exempt retaining wall must still comply with the Building Code, which in practice means:
- Structural stability. It must hold up the ground for its life without moving or tilting.
- Drainage. Groundwater behind the wall has to be drained away, usually with a perforated drain at the base wrapped in filter fabric and surrounded by free-draining aggregate, discharging to an approved outlet.
- Durability. Materials must suit the job. Timber poles used in the ground for retaining are typically H5 treated.
- Safety from falling. Where people could fall from the top of a wall, Building Code clause F4 can require a barrier.
You're responsible for making sure exempt work complies, so keep photos of the drainage and footings before backfilling.
Which planning rules still apply?
Building consent and resource consent are separate. Even a consent-exempt wall can be caught by the Auckland Unitary Plan:
- Earthworks (chapter E12). Cutting and filling to build the wall counts toward earthworks limits, which vary by zone and overlay. See the earthworks consent guide.
- Boundaries. Walls near boundaries can be affected by yard and height-in-relation-to-boundary rules, especially with a fence on top.
- Overland flow paths and flooding. A wall must not block or divert flood flows onto neighbours.
- Trees and overlays. Notable trees, heritage and ecological overlays can add rules.
- Public pipes. Building over or near public stormwater or wastewater pipes needs approval.
What about a fence on top of a retaining wall?
A fence on top adds height and wind load. Planning rules look at the combined height near boundaries, and the fence can act as the safety barrier where people could fall. Design the wall and fence together. A fence fixed to the top of a wall that wasn't designed for it is a common cause of leaning walls.
What if the wall needs consent?
- Engineering design. An engineer designs the wall for the site's ground, surcharges and drainage, often with a geotechnical assessment. The engineer provides a producer statement for the design (PS1).
- Building consent application to Auckland Council with the drawings and specification.
- Construction and inspections. Council inspects at key stages (for example, foundations or pole holes before concrete), and the engineer may observe and provide a construction review statement (PS4).
- Code compliance certificate once the work is finished and inspected.
What if a previous owner built an unconsented wall?
If a wall should have had consent and didn't, you can apply to Council for a certificate of acceptance. Expect to provide evidence of how it was built, and possibly an engineer's assessment. If the wall is failing, repair or replacement under a new consent may be the simpler path.
Ambient Civil designs (with engineers) and builds timber, block and gabion walls across Auckland and handles the consent when it's needed. Book a free site visit, or read the retaining wall cost guide.
Sources and further reading
- Building Performance (MBIE): Retaining walls up to 1.5 metres depth of ground (Exemption 20)
- Auckland Council: Build a retaining wall (consent checker and guidance)
- Building Performance (MBIE): Building work that doesn't need a building consent
- Auckland Unitary Plan, Chapter E12: Land disturbance β District
- Auckland Unitary Plan (Operative in part)
General information only. Every site is different: consent, engineering and safety requirements depend on your property, so check with Auckland Council or a qualified professional, or ask us for a free site visit.
About this guide. Written by the Ambient Civil team: 22 in-house crew and 20+ years of civil construction, demolition and earthworks across Auckland. Rules and licence requirements are summarised from the official sources listed above and were checked on . Rules change, so confirm your property's position with Auckland Council or a qualified professional.